本文发表在 rolia.net 枫下论坛SCHEDULE
Schedule ‘A’ - Exemption to Requirement for Permit
Notwithstanding Section 967.2.1, no site alteration permit shall be required
for:
1. emergency work performed in consultation with the Town, subject to
any requirement from the Commissioner to obtain a permit for the continuation
of such work;
2. cultivation or tilling of garden beds so long as such work does not
have an adverse effect on existing drainage patterns on abutting properties;
3. the removal of topsoil incidental to a normal agricultural practice including
such removal as an incidental part of sod-farming, greenhouse operations
and nurseries for horticultural products; and
4. minor landscaping works, as determined at the sole discretion of the
Commissioner, which are at least 0.6 metres from any property line and do
not impact drainage patterns on abutting properties.
The exemption from the permit requirements under this Chapter granted
to site alterations listed in this Schedule do not provide an exemption from
other provisions of this Chapter. All site alterations shall be performed in
compliance with applicable provisions. By-law 166-07, 10 December,
2007; Schedule ‘A’.
DUMPING - FILL - SITE ALTERATIONS
OCTOBER更多精彩文章及讨论,请光临枫下论坛 rolia.net
Schedule ‘A’ - Exemption to Requirement for Permit
Notwithstanding Section 967.2.1, no site alteration permit shall be required
for:
1. emergency work performed in consultation with the Town, subject to
any requirement from the Commissioner to obtain a permit for the continuation
of such work;
2. cultivation or tilling of garden beds so long as such work does not
have an adverse effect on existing drainage patterns on abutting properties;
3. the removal of topsoil incidental to a normal agricultural practice including
such removal as an incidental part of sod-farming, greenhouse operations
and nurseries for horticultural products; and
4. minor landscaping works, as determined at the sole discretion of the
Commissioner, which are at least 0.6 metres from any property line and do
not impact drainage patterns on abutting properties.
The exemption from the permit requirements under this Chapter granted
to site alterations listed in this Schedule do not provide an exemption from
other provisions of this Chapter. All site alterations shall be performed in
compliance with applicable provisions. By-law 166-07, 10 December,
2007; Schedule ‘A’.